Project documents list

Note: Some links require login.

Project phase Document Purpose Content Prepared by Approved by Notes
Initiate Project request or statement of work A description of products, services, or results to be delivered by the project  Business need, product scope description, alignment with strategic plan  Customer or project initiator Governance  
  Business case To determine if project is worth the investment  Cost benefit analysis including total cost of ownership  Business or financial analyst Governance  
  Project charter Formally authorizes the project Project purpose, project objectives and success criteria, high-level requirements, high-level risks, summary milestone schedule, summary budget, stakeholder list, project approval requirements, roles and responsibilities Sponsor and project manager Sponsor(s)  
Plan Project plan (combination of sub plans)     Project manager and project team Sponsor(s), applicable resource managers With the exception of the baselines, all project documents are living documents that are updated as the project is executed
  Scope baseline Baseline for tracking scope Defines the scope in detail Project manager and project team Sponsor(s), applicable resource managers  
  Detailed requirements Baseline for tracking requirements Defines requirements and completion criteria in detail tied to deliverable(s) Project manager and project team Sponsor(s), applicable resource managers  
  Schedule baseline Baseline for tracking schedule WBS structure, detailed activity list with dependencies, milestones Project manager and project team Sponsor(s), applicable resource managers This is not a form but is completed in a tracking tool  (e.g., Basecamp or MS Project)
  Cost baseline Baseline for tracking cost Detailed cost breakdown for personnel, nonpersonnel operational and capital expenses, including contingency reserves Project manager and project team Sponsor(s), applicable resource managers  
  Risk management Identification and strategies for managing risks Outlines risks, prioritizes them, and provides mitigation strategies Project manager and project team Sponsor(s), applicable resource managers  
  Stakeholder management Outlines stakeholder management Identification, assessment, and classification of project stakeholders Project manager and project team This is an internal document for the project manager This is an internal document for the project manager
  Communications Outlines communication strategy, tools, and techniques to be used Describes how, when, and by whom information about the project will be administered and disseminated Project manager and project team Sponsor(s), applicable resource managers  
  Project governance Outlines how the project will be governed Outlines project success metrics, change management procedures, meeting and sponsor reporting cadence, and thresholds for action Project manager Sponsor(s), applicable resource managers This will likely be standard for all projects unless there are exceptions
  Procurement Identifies all contracts and who manages them List of contracts, who manages them, and close-out criteria Project manager Sponsor(s), applicable resource managers  
  Project kick-off Standard project kick-off agenda Outlines project kick-off agenda Project manager N/A  
Execute Change request Request form to modify or add a requirement or deliverable Outlines impact and schedule for requested change Sponsor, client, or team member Project change control board  
  Change control log History of requests and their status Records each request and if approved/implemented or put on hold Project manager N/A  
  Issue log Documents project issues Issue and person assigned person to resolve Project manager N/A  
Monitor and control Project status meeting template Outlines format for project status meeting Notes and action items for each meeting Project manager N/A  
  Individual project status report Provides scheduled updates to sponsors Status on budget, schedule, scope, risks, and key milestones Project manager N/A Weekly or biweekly depending on sponsor 
  Consolidated dashboard Provides high-level project status Consolidated status for budget, schedule, and scope Project manager N/A Biweekly report
Close Project sign-off Authorizes the project to be released Deliverable status, outstanding issues, and final QA report Project manager Sponsor(s)  
  Lessons learned Provides a history of project success/failures as a reference for future projects Documents projects failures, successes Project manager and team  N/A  
  Transition to operations checklist and documentation Provides project/product information so operations can successfully maintain Development support contacts, outstanding issues and work-arounds, product documentation and training manuals Project manager and team  Operations  