Portfolio dashboard project status guidelines
| Constraint |
Project is proceeding on or near plan. |
Issues identified that may impact the project. High confidence the project team will resolve. |
Issues identified that impact the project and are outside of the control of the project team. Escalation is necessary. |
|---|---|---|---|
| Health | At least two (2) constraints are green and none is red. | At least two (2) constraints are yellow and none is red. | One or more constraints are red. |
| Scope | No scope changes or approved scope changes that reset the baseline. | Emerging, unapproved scope changes expected to be resolved by the project team. | Scope changes that require escalation for resolution. |
| Schedule | No schedule changes or approved schedule changes that reset the baseline. | Emerging schedule changes expected to be resolved by the project team. | Schedule changes that require escalation for resolution. |
| Budget | No budget changes or approved budget changes that reset the baseline. | Emerging budget changes expected to be resolved by the project team. | Budget changes that require escalation for resolution. |